I-75 at SR 884 (Colonial Boulevard)

Download the Final Study (PDF, 8.1MB)

Executive Summary

The Florida Department of Transportation (FDOT) is conducting this Interchange Modification Report (IMR) re-evaluation for the I-75 at SR 884 (Colonial Boulevard) interchange, located in Lee County, Florida. I-75 is a six lane (three lanes in each direction) north-south interstate facility in the vicinity of the existing SR 884 interchange. The posted speed limit on I-75 is 70 mph. SR 884 is a six-lane divided urban principal arterial in the vicinity of the interchange.

The IMR was approved on August 7, 2017 documenting the future reconstruction of the interchange to a Diverging Diamond Interchange (DDI) configuration. Other improvements along SR 884 include a Continuous Flow Intersection (CFI) to the west at the intersection of Six Mile Cypress Parkway/Ortiz Avenue and a Superstreet intersection to the east at the Forum Boulevard intersection. The approved 2017 IMR also considered construction of northbound and southbound auxiliary lanes on I-75 between the SR 884 and SR 82 (MLK Jr. Boulevard) interchange to the north. Reconstruction of the interchange is scheduled to be let in June 2020 and will proceed as a design-build project.

This re-evaluation of the IMR is developed in accordance with the FDOT Policy No. 000-525-015, “Approval of New or Modified Access to Limited Access Highways on the State Highway System (SHS)”; FDOT Interchange Access Request User’s Guide (IARUG), New or Modified Interchanges FDOT Procedure No. 525-030-160; and the Project Traffic Forecasting FDOT Procedure No. 525-030-120.

The objective of the IMR re-evaluation is to accommodate the following proposed modifications to the approved 2017 IMR concept as part of the design-build process:
  • The northbound on-ramp at the I-75 at SR 884 interchange will be widened from the approved one lane to proposed two lanes at the gore point to provide for improved operations at the ramp merge area.
  • The I-75 southbound off ramp at the SR 884 interchange will be widened from the existing one lane to two lanes at the diverge point from the mainline.
  • Similarly, the northbound off ramp at the I-75 at SR 82 interchange will be widened from the existing one lane to two lanes at the diverge point from the mainline.


Purpose and Need

Download the Purpose and Need (PDF, 113.1KB)

The purpose and need for the interchange modifications were identified in the previously approved 2017 IMR and are summarized below:

  • To help serve travel demands created by anticipated countywide population and employment growth and is anticipated to contribute to better traffic operation.
  • To enhance overall safety, capacity, and mobility within Lee County, since SR 884 is a major principal arterial and the future land use designation along this corridor is intensive commercial.
  • SR 884, a regional facility, is part of the evacuation route network established by the Florida Division of Emergency Management. The improvements to interchange of I-75 and SR 884 are anticipated to enhance evacuation capacity and traffic circulation, which will improve evacuation and response times


Recommended Alternative

Download the Recommended Alternative (PDF, 2MB)

Please see the attached recommended alternative

Travel Time Savings

Safety Benefits

Download the Safety Benefits (PDF, 193.2KB)

Please see the attached safety report for more information.